CONSERVATION work on a section of what is believed to be Ireland’s oldest house is nearing completion in Ennis. Scaffolding was taken down from Ms Irene Clune’s house (better known as McParlands) last week to reveal the building’s historic triple diamond stone Jacobean chimney for full viewing for the first time in three years.
The building’s triple diamond stone Jacobean chimney has been an icon of medieval Ennis for centuries. The house has undergone necessary structural repair work in recent months. It has been estimated that the works will cost € 170,000 to complete.
Conservation and repair work at the site has revealed that the building’s timber frame interior dates back to the 1500s.
Conservation officer Dick Cronin explained that work on the building’s exterior is almost complete. He said, “We believe it’s the only half-timber frame house left in Ireland. We have to do dendrochronological analysis of the timber. Once it is tested, we will be able to trace it back to the exact year when the tree was cut down.”
Mr Cronin added, “They are doing work on the shopfront which dates back to the 1800s and that is almost finished.”
It has been suggested that the building could be used as a museum but, according to Town Manager, Ger Dollard, the building will be returned to its former use as a home. He explained, “Our priority is to complete the works under the Dangerous Structures legislation and allow Ms Clune go back to her home as soon as possible. There are no other plans for the use of the building other than returning it to its former use as a dwelling.”
During October 2011, the gable and chimney were carefully taken down and stored. The Conservation Contractor, Tom Howard, claims it was “the most dangerous and precarious job I have ever undertaken as a builder but thankfully everything went to plan”.