REMEDIAL works on 17 local authority houses in Scariff have been completed, at a cost of € 850,000.
The Mayor of Clare, Councillor Christy Curtin (Independent), was handed the keys of the 17 units at Connaught Road, Scariff, on Friday, following the completion of the project.
The project contract, which was awarded to Galway construction company Atlantic Developments Limited in October, involved upgrade works to the 17 tenanted properties in the estate. This included insulation, roofing, windows and doors replacement.
The houses are part of a batch of 31 homes which were constructed in the 1970s. The remaining 14 houses have since been purchased.
New heating systems, including high efficiency oil boilers supplemented with solid fuel stoves, have been upgraded to achieve a C1 Building Energy Rating (BER). Solar panels also have been provided on the roofs of four bungalows to achieve a high energy rating.
Other works include general environmental drainage and a new watermain, boundary treatment to all 31 houses, and improvement works to roads, public lighting and footpaths in the estate.
“The improvement to the energy efficiency of these houses in Scariff will make a great difference to the comfort factor for the occupants. I would like to acknowledge the excellent work carried out by the contractor and design team who successfully completed the project on time and within budget,” said Mr Curtin.
The Chairperson of the Council’s Housing Strategic Policy Committee, Cllr Patricia McCarthy (Independent), thanked residents for their “forbearance and co-operation while their homes were being upgraded”.
“Many residents voluntarily relocated for the duration of the works while those who remained in residence co-operated fully with the contractor and tolerated a level of inconvenience. They can now look forward to enjoying an improved quality of life in their upgraded homes,” she said.
The project funding of € 850,000 was provided by the Department of the Environment, Heritage and Local Government.